Prudentia Process Consulting were engaged to perform FEED and detailed multidiscipline engineering services for a <$10M TIC cooling tower replacement. This included all process, mechanical, civil/structural & electrical design and drafting works. Prudentia Process Consulting also developed the demolition and installation scope of work for execution, support equipment procurement by developing and later evaluating tender packages. Prudentia Process Consulting also provided vendor management services on behalf of the client to over the cooling tower implementation.

Prudentia was engaged by Alpha HPA as the principal engineers to the HPA First Project, to deliver the 12 week Front End Engineering and Design (FEED), ahead of the Engineering, Procurement and Construction Management (EPCM) for the PPF. Alpha and Prudentia have been working closely on the HPA First Project since 2017, with Prudentia authoring both the Pre-Feasibility Study (March, 2019) and the Definitive Feasibility Study (March, 2020) for the Project. Refer to ASX Announcement ASX:HPA Dated 1st June 2021 Microsoft Word – ASX Draft_PPF_V10 (alphahpa.com.au)